U-Tapao airport build to start in 2027, first terminal phase due 2031
· Transport, Business

The company behind the U-Tapao airport project, U-Tapao International Aviation Co., Ltd. (UTA), says construction of the new airport and the surrounding Eastern Aviation City will begin in 2027. The first phase is planned to be finished in 2031.
The passenger terminal will grow in steps. Phase one is sized for 3 million passengers a year and is estimated at 10 billion baht. Each new stage is due to start once traffic reaches 80 percent of the current capacity, with a long-term ceiling of 60 million passengers a year.
The second runway is already being built. It will be 3,505 metres long and 60 metres wide, with new taxiways, lighting, power and drainage. The contract is worth 13.142 billion baht over about three years. The work is roughly 35 percent done and is scheduled to finish at the end of 2028.
An aircraft maintenance centre is also planned on a 210-rai site. Bangkok Airways will develop 30 rai of it, investing 1 billion baht in a first phase with one hangar able to hold two Airbus A320s. That phase is due to open in 2029, with a second hangar for other airlines later.
UTA has not said how the work will affect current flights. For now, passengers flying in and out of U-Tapao, the airport south of Pattaya, use the existing terminal.
More news
EventsFireworks Festival: Beach Road closed again for the final night
Beach Road and the central sois close to traffic from 3pm on both festival days, so plan to walk, park early or come in from the north or south.
EventsCity warns beach businesses not to overcharge during the fireworks
Pattaya City told beachfront operators to keep normal prices during the festival and asked anyone charged unfairly to call the 1337 hotline.
SafetyBoat safety checks at South Pattaya Pier
Marine officials and police inspected tour and ferry boats at South Pattaya (Bali Hai) Pier on 26 November and reminded crews that every passenger must wear a life jacket.